Graphics Version
Logo

Homepage > ... > Parks & Facilities > The Planning Process > Parks in the Works

Parks and Facilities in the Works


Projects in DesignProjects under Construction


Rehabilitation Projects

Unscheduled Projects


Projects in Design


Harry Crabb Park - Phase 2

Approved Master Plan

Location:
1000 Scarborough Dr, at the corner of Secret Ravine Pkwy.

Description:
This park site is 18.8-acres in size and will include lighted baseball and softball fields, lighted tennis courts, a junior soccer field, a permanent restroom/snack bar, a shaded and enclosed play area, picnic areas and off-street parking.

Biography:
This park has been named after Harry Crabb, a former Mayor, former member of the Roseville City Council and Planning Commission. Harry has served the residents of Roseville for over 25 years and is a strong supporter of youth sports activities.

Phase 2:
Construction documents for a $2.5 million phase 2 intends to complete the park's development with the exception of a few amenities, which will be added at a later date when additional budget becomes available.  The maintenance of this park is general funded.  The project will be bid for construction pending the drought situation. If the City shifts below a Stage 2 drought level, the project will move forward.

Volleyball Court Construction:
Construction on the volleyball courts began Monday, June 15th to re-direct the existing courts to face North (toward Scarborough Dr.). Existing poles will be replaced with professional grade poles. Construction is expected to end by June 30th, 2015.   


  
Hughes Park Bridge & Bike Trail Extension

 

Location:
1600 Parkside Way, off Diamond Creek north of Blue Oaks Boulevard

Description:
This project will construct a bridge and bike trail extension to connect Hughes Park to Bent Tree Drive.

  Timeline:
  A design-build contract has been awarded. Permitting and design refinement is underway.  Targeting late 2015 for construction.

back to top 


Stone Point Neighborhood Park Site



Location:
Stone Point Drive between N. Sunrise and Rocky Ridge

Description:
3 acre neighborhood park. 
This park will be built by Taylor Morrison on behalf of the City.

Timeline:
Projected start of construction is Summer 2015.


 F-50 School/Park Site


(double click image to view large, "ctr/+" to zoom in)

Location:
4151 Brick Mason Circle

Public Workshops:
Click below to read the meeting minutes from the public workshops that were held regarding this park:
Meeting Minutes 9.30.14
Meeting Minutes 1.22.15
Meeting Minutes 6.2.15

Description:
8 acre school/park site adjacent to Fiddyment Farm Elementary School.
The preliminary sketch attached is formalized based on resident feedback at the January 22nd public meeting. This illustrated Master Plan was posted for a two week public write-in period April 6th - April 17th for the residents to weigh in. The Master Plan will be submitted to the Parks and Recreation Commission for review on Monday, July 6th.  The meeting starts at 7:00pm at the Council Chambers, 311 Vernon St. Roseville, CA. This is a public meeting.
 
Timeline:
 
Construction is targeted for late 2015.


  
SSP 56 Park Site



Location:
Stoneridge

Description:
This is a turn-key park site proposed by Elliott Homes in Stoneridge.  Construction is targeted for late 2015.

  
Central Park Phase 3



Location:
This regional park is proposed to contain two lighted youth softball fields, a lighted soccer field and multi-use field, picnic areas, an indoor pool facility, on-site parking, basketball courts, central plaza, a children’s play area and swing area as well as an interactive water play area. Phase 1 of this project included a soccer field, underground utilities and concrete pathways.  Phase 2 construction is complete and includes a children's play area, swings, shaded picnic area and a half-court for basketball.  Phase 3 work has yet to be defined. 

Public Workshops:
Click below to read the meeting minutes from the public workshops that were held regarding this park:
January 6, 2005 Meeting Minutes
Meeting Summary from February 15, 2012
Handout from February 15, 2012 Meeting

Timeline:
Phase 3 construction is late summer 2015, pending drought situation.


Projects under Construction



  back to top
Rehabilitation Projects
  
Garbolino Park Rehabilitation 

Location:
1015 Camelia Avenue

Description:
The project will include removal of existing play equipment, swings and sand.  New play equipment, site material and an ADA ramp will be installed.    

Timeline:
Construction is targeted to begin June 2015.


 
Mel Hamel Park Restroom Install

Location:
10080 Crocker Ranch Road

Description:
The project will include installation of a new restroom.

Timeline:
Construction targeted for late Summer 2015. 
 

back to top



Unscheduled Projects

Park construction priorities are evaluated on an annual basis. Priorities are established based on projected build-out, available funding, location related to other existing parks and demand. While we endeavor to build all of our parks as quickly as possible for the use and enjoyment by the citizens of Roseville, resources can limit the number of parks built in a single year. Construction of the following park sites is currently unscheduled:


Sports Complex

Location:
Blue Oaks Blvd / Phillip Road / Hayden Parkway

Description: 
Current discussions involve the layout and variety of amenities for the site.  Phase 1 amenities being considered: multiple lighted synthetic soccer/multi-sport fields, restrooms, storage facilities, children's playground area(s), shaded picnic area(s), and pedestrian pathway through landscaped area. 

Timeline:
The start of construction has not yet been determined.
  

back to top
Gibson Drive Park Site (NCRSP 56)

Location:
Gibson Drive and Roseville Parkway

Snapshot:
The Master Plan has not yet been developed.

back to top
Reason Farms Environmental Preserve



Location:
Northwest of the West Roseville Specific Plan

Description:
In May 2003, the City Council approved the acquisition of two parcels of land, the Reason Farms and Warnick properties, totaling approximately 1700 acres along Pleasant Grove Creek. This property was acquired for the purpose of constructing a storm water retention basin, but will also provide many potential open space and recreation opportunities for the City of Roseville.

Timeline:
Project is on hold pending outcome of retention basin reconfiguration for storm water/flood protection.

Snapshot:
A preliminary concept plan has been developed, however the plan must be revenue-neutral or better before environmental clearance efforts are undertaken.

back to top
Sun Tree Park



Location:
1101 Sunrise Avenue, located within the existing Sunrise Greenbelt near Sun Tree Drive

Description:
This 0.2-acre park will add a small picnic area, swing area and children's play area to the large existing greenbelt.

Snapshot:
Project is on hold pending additional funding.

back to top
Village Center
 


Location:
Pleasant Grove Blvd between Village Plaza Drive and Village Center Drive

Status:
The concept plan was developed in 2009 and approved by the City Council in February 2010.  It is not slated to move forward due to funding and ongoing maintenance obligations.  The site is intended to compliment the surrounding commercial area.  No movement on the commercial development has occurred to date.

back to top


SEARCH   

Homepage | Residents | Business | Visiting | Departments | e-Services | Apply | Find | Report | Sign Up
City of Roseville 311 Vernon St., Roseville, CA 95678. Phone: 916-774-5200.
Powered by Civica Software