Project area
Because of the scope and size of the project, we are working in phases to help reduce customer impacts. See image to the right for details.
Construction schedule
- Timeline: February 2021 and finish by December 2021.
- Construction hours: weekdays, approximately 7 a.m. – 5 p.m.
- Initial construction activities will be to pothole for potential utility conflicts.
- After potholing water main construction will be phased by areas.
Tentative phasing schedule is below. Please note: this schedule will be updated as the project progresses.
Phase
|
Area Name
|
Water Main and Service Connections
|
Temporary Pavement Restoration
|
Road Resurfacing
|
1
|
Folsom Road
|
complete
|
complete
|
September 2021
|
2
|
Bonny Knoll/Melrose
|
complete
|
September 2021
|
Spring-Summer 2022
|
3
|
Hillcrest West/School
|
complete
|
September 2021
|
Spring-Summer 2022
|
4
|
Hillcrest East
|
Finish 8/20/21
|
September 2021
|
Spring-Summer 2022
|
5
|
Sunrise Ave
|
Finish 9/1/21
|
October 2021
|